213 railway projects report cost overrun of Rs 1.73 lk cr


Team Udayavani, Feb 25, 2018, 12:33 PM IST

New Delhi: More than three-fifths of the total 349 delayed central projects belong to the railways sector causing a cost overrun of Rs 1.73 lakh crore, according to a report by the statistics ministry.

A total of 213 projects of railways are facing delays due to various reasons, leading to cost overrun of Rs 1.73 lakh crore, the report of the Statistics and Programme Implementation ministry for October 2017 mentioned. 

The statistics ministry monitors central sector projects envisaging an expenditure of Rs 150 crore and above each on regular basis. According to the report, the original cost of these 213 railway projects was Rs 123,103.45 crore. 

The total anticipated cost of the projects has ballooned to Rs 2,96,496.70 crore now due to delays, which shows overall cost escalation of 140.85 per cent. The ministry monitored 350 projects of Indian Railways in October this year. 

The report stated that as many as 36 projects of railways out of the monitored 350 projects reported time overrun or delay of 12 months to 261 months. After railways, power sector reported the second highest incidence of overall cost overrun. Of the 126 power projects monitored by the statistics ministry, 43 reported cost overrun of Rs 58,728.23 crore. 

The total original cost of these 43 projects was Rs 104,449.62 crore which escalated to total anticipated cost of Rs 163,178.45 crore. The report stated that out of the 126 power sector projects, 64 reported time overrun (delay) of 2 months to 136 months.

Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.

Top News

Omicron is the new COVID kid on the block: Five steps to avoid, ten to take immediately

Being ‘punished’ for early detecting new COVID-19 variant Omicron: South Africa

Karnataka Congress demands inquiry by SC Judge or House panel into graft charges by contractors

If Hindus want to remain Hindus then Bharat should be made ‘akhand’: RSS chief

Italy, Germany report cases of omicron COVID-19 variant

B’luru: Two South Africans test positive for COVID-19 as threat of new variant looms

Will fight till my last breath for restoration of JK’s special status: Omar Abdullah


Related Articles More

If Hindus want to remain Hindus then Bharat should be made ‘akhand’: RSS chief

Will fight till my last breath for restoration of JK’s special status: Omar Abdullah

Several Muslims including Javed Akhtar, Naseeruddin Shah oppose anti-blasphemy law demand

4 health dept officials to monitor screening at international airports in TN

Bihar: Village votes for dead candidate to honour dying wish. He won!

MUST WATCH

Gopal Naik Alevoor | How to do Vermicomposting Business in India and its uses

ನಂಬಿ ಬಂದವರ ಸರ್ವ ಕಷ್ಟ ಪರಿಹರಿಸುವ ತಾಯಿ ಚಾಮುಂಡೇಶ್ವರಿ

NEWS BULLETIN 27-11-2021

Kustagi Viral Video

Wild boar creates havoc at car showroom; Video goes viral


Latest Additions

Omicron is the new COVID kid on the block: Five steps to avoid, ten to take immediately

Being ‘punished’ for early detecting new COVID-19 variant Omicron: South Africa

Karnataka Congress demands inquiry by SC Judge or House panel into graft charges by contractors

If Hindus want to remain Hindus then Bharat should be made ‘akhand’: RSS chief

Italy, Germany report cases of omicron COVID-19 variant

Thanks for visiting Udayavani

You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.