GAIL completes Kochi-Mangaluru pipeline


PTI, Nov 16, 2020, 6:37 PM IST

Kochi: The much-delayed Kochi-Mangalore natural gas pipeline project is finally ready for commissioning any day from now as the national energy major GAIL India has completed the final 540-metre treacherous stretch across the Chandragiri river in northern Kerala, according to a senior company official.

The 444-km long natural gas pipeline was launched in 2009 at an estimated cost of Rs 2,915 crore and was to be commissioned in 2014. But opposition on safety and commercial grounds wherein the land price was the main hurdle, both from political parties and the public, ensured that the project lingered on.

This led to the project cost nearly doubling to over Rs 5,750 crore.

“We have completed the most difficult stretch across the Chandragiri river in Kasargod district in northern Kerala, on Saturday. Now the testing is on and this will be completed in the next two days. Within this week itself gas will reach Mangaluru through the 444-km pipeline,” P Murugesan, the executive director and head of Southern region, Gail, said from Bengaluru on Monday.

A formal commissioning will be done later, according to the availability of the minister, he added.

The pipeline is charged up to Kannur now and is live up to Kuttanad in Palakkad district, 90 km north of Kochi since June 2019 and of the remaining 354 kilometres, the line is ready up to Kannur.

Kuttanad is the main junction of the project as from here the line bifurcates to Mangaluru and Bengaluru.

The first phase of the project was commissioned in August 2013 in the Kochi metropolitan area with industrial supplies and domestic supplies from February 2016 by Adani Gas.

Today the pipeline supplies 3.8 million cubic metres of gas every day to industrial and residential customers in Kochi and is set to cross 4 million cubic metres soon in the city itself, while Mangaluru has a potential of 2.5 million cubic metres per day, Murugesan said.

With the commissioning of the pipeline, gas demand in the State will touch 80-90 million cubic metres per annum from 60 million cubic metres now.

The pipeline is a big boost to the struggling Kochi LNT Terminal of Petronet which has a capacity of 5 million tonne annually but 90 per cent capacity has been idling due to the delay in completing the Kochi-Mangalore pipeline and Murugesan said with the commissioning the capacity utilisation of the LNG terminal will go up to 25-30 per cent.

Apart from huge environmental gains, the State can also gain monetarily as it can get up to Rs 1,000 crore by way of taxes alone. Supplying to the Kochi region alone helps the State earn over Rs 340 crore annually in tax revenue.

The authorities were ready to complete the project this August but a 540-metre stretch across the Chandragiri river became a nightmare for them. So as a way out they reduced the diameter of the pipe to a fourth – from 24 inches to just 6 inches now.

But Murugesan said this is a temporary arrangement and the work to lay 24-inch pipe will resume soon after commissioning of the project and once ready the switch-over will not disrupt gas supply.

He also said the pipeline will supply to all the seven districts it passes through in the State – Ernakulam, Thrissur, Palakkad, Malappuram, Kozhikode, Kannur and Kasargod – as well as the hilly Wayanad district. Of these already city gas distribution is on in Kochi where its supplies 3.8 million cubic metres of gas every day.

The company was working on the 540-metre river stretch since late April but got inordinately delayed as this stretch goes up to 8 metres deep in the river bed at some places and has an elevation difference of 148 metres, as the river flows down a deep valley, making it one of the rarest engineering projects for the entire pipeline network across the country.

The project crosses as many as 96 water-bodies south of the Chandragiri river. The problem with this stretch is that the river flows down through a valley to the Arabian Sea, forcing them to drill horizontally from under the river bed.

The EPC contractor for this stretch was awarded to NR Patel & Company.

Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.

Top News

ADB approves $190 mn loan to upgrade Bengaluru’s power distribution system

India beat Australia by 11 runs in first T20 International

SC sends notice to K’taka govt over Ragini’s bail plea in drugs case

K’taka: Expert panel recommends banning New Year public celebrations

COVID-19 vaccination drive after scientists’ nod: PM Modi

Indian Navy an outstanding force: Defence Minister Rajnath Singh on Navy Day

1,525 kg of explosives, 6,000 detonators seized in Meghalaya, 6 arrested



Related Articles More

K’taka COVID-19 update: 1247 new cases, 877 discharges, 13 dead on Dec 3

ADB approves $190 mn loan to upgrade Bengaluru’s power distribution system

COVID-19 vaccine should be kept affordable, free of cost for economically vulnerable: Deve Gowda

Belagavi: Soldier martyred in Srinagar encounter

Mangaluru: Youth hit by car while crossing road in critical condition

MUST WATCH

M’luru boat tragedy: Search operation still on for Ansar’s body

Deer falls into well, rescued

Without sulking from his illness, this young man changed his life through agriculture

State government must immediately bring in anti-cow slaughter law: Sri Vishwa Prasanna Tirtha Swamiji

Hamsa Chaitanya Desi Outlet | Desi Products Store Udupi | Documentary by Udayavani

Latest Additions

Chargesheet Filed Against Arnab Goswami, Two Others in 2018 Abetment to Suicide Case

Govt Procures 330 Lakh Tonnes of Kharif Paddy So Far at MSP for Over Rs 62,278 Crore

India Economy Likely to Contract by 10% in FY21, Says Former Planning Commission Member Abhijit Sen

K’taka COVID-19 update: 1247 new cases, 877 discharges, 13 dead on Dec 3

Vijay Mallya’s Property in France Worth Rs 14 Crore Seized under PMLA: ED

Thanks for visiting Udayavani

You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.