357 infra projects show cost overruns of over Rs 3.39 lakh crore


Team Udayavani, Nov 11, 2018, 1:24 PM IST

New Delhi: As many as 357 infrastructure projects, each worth Rs 150 crore or above, have shown cost overruns to the tune of over Rs 3.39 lakh crore owing to delays and other reasons, a report said.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.

“Total original cost of implementation of the 1,362 projects was Rs 17,03,840.01 crore and their anticipated completion cost is likely to be Rs 20,43,024.21 crore, which reflects overall cost overruns of 3,39,184.20 crore (19.91 per cent of original cost),” the ministry’s latest report for June 2018 said.

Of these 1,362 projects, 357 reported cost overruns and 272 time escalation.

According to the report, the expenditure incurred on these projects till June 2018 is 7,86,754.10 crore, which is 38.51 per cent of the anticipated cost.

However, it said the number of delayed projects decreases to 198, if delay is calculated on the basis of latest schedule of completion.

For 667 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 272 delayed projects, 65 projects show delay in the range of 1 to 12 months, 53 projects have 13 to 24 months delay, 74 projects reflect delay of 25 to 60 months and 80 projects show 61 months and above delay.

The brief reasons for time overruns as reported by various project implementing agencies are delay in land acquisition, forest clearance, supply of equipment.

Besides, there are other reasons like fund constraints, geological surprises, problems in equipment erection, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by the contractor, maoist problems, court cases, contractual issues, ROU/ROW (right of use/right of way) problems, law and order situation etc.

It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.

Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.

Top News

Siddaramaiah orders SIT probe over alleged sex scandal involving Deva Gowda’s grandson

Auto rickshaw driver brutally murdered in Kozhikode

‘PM has been fighting for Shivaji’s principles’

YSRCP Social Media team diligently connects with voters in Andhra Pradesh

Space enthusiasts ask ISRO chief if agency can find water on moon

Actor Sahil Khan detained by Mumbai SIT in Mahadev betting app case

MDH says its products are safe; rejects pesticide allegations

Related Articles More

Pune court asks police to probe bribery allegations against IT major Cognizant

Patanjali Foods to evaluate proposal to buy Patanjali Ayurved’s non-food business

Nifty, Sensex rally for 6th day running on firm Asian peers; Tech Mahindra jumps over 12%

IndiGo, Air India plan to purchase up to 170 wide-body planes in little over a year

Kotak Mahindra Bank shares tank 13%; mcap erodes by Rs 37,721 crore post RBI action

MUST WATCH

Skin Rash, Causes, Signs and Symptoms

11 bullets found in python’s body!

K. Jayaprakash Hegde Sharing His Memories

Grafting Jack Anil

Heat Illness


Latest Additions

Siddaramaiah orders SIT probe over alleged sex scandal involving Deva Gowda’s grandson

T20 World Cup: Agarkar to have informal selection meeting with skipper Rohit Sharma in Delhi

Archery WC: Indian men’s team upset Olympic champions Korea to bag historic gold after 14 years

PM deflecting from failures, should address real issues, says Chidambaram

Auto rickshaw driver brutally murdered in Kozhikode

Thanks for visiting Udayavani

You seem to have an Ad Blocker on.
To continue reading, please turn it off or whitelist Udayavani.