Pumpwell flyover likely to open for traffic on Jan 31
Team Udayavani, Jan 29, 2020, 9:59 AM IST
Photo Credits: Satish Ira
Mangaluru: After a long delay of almost ten years, with several deadlines being missed, the Pumpwell flyover, part of the four-laning of Talapady-Kundapura stretch of National Highway 66, is likely to be open for traffic from Friday, January 31.
Work on four-laning NH 66 between Talapady-Kundapur, excluding the Nanthoor-NITK Surathkal stretch, started in September 2010 and Pumpwell (Mahaveera Circle) flyover was a part of the project. Concessionnaire M/s Navayuga Udupi Tollway Pvt., Ltd., failed to execute many flyovers on the stretch within the prescribed time, including Thokkottu and Pumpwell in Mangaluru, Karavali Circle in Udupi, and Shasri Circle in Kundapur.
Mangaluru South MLA Vedayvas Kamatha speaking to Udayavani said that the flyover work is almost completed and is likely to be inaugurated on January 31.
Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.
Top News
Related Articles More
MLC polls: Why party ignoring 50 pc of population, asks Cong leader Kavitha Reddy
B’luru: KSRTC conductor punches, kicks woman passenger; arrested
Textbook revision done in interest of children: B C Nagesh
Kunigal: 19-yo girl student killed in bike accident
Textbooks revision row: BJP will lose its base in Karnataka, says Kumaraswamy
MUST WATCH
Latest Additions
Newborn, found alive after being buried, dies at Srinagar hospital
Dawood is in Karachi, would send Rs 10 lakh per month to kin: Witnesses in money laundering case tell ED
MLC polls: Why party ignoring 50 pc of population, asks Cong leader Kavitha Reddy
Sri Lanka: PM Ranil Wickremesinghe appointed Finance Minister by Prez Gotabaya
B’luru: KSRTC conductor punches, kicks woman passenger; arrested